The first step is a visit from our site engineer to identify the appropriate installation point and sensor for the job.  A wiring plan will then be produced for approval and any additional hardware (for example automatic sampler) identified which the client will be expected to complete prior to installation.

The installation of the sensors usually takes a day followed by set up, calibration and commissioning by the Agentis Innovations engineer.

Posted in: Moisture Measurment & Control