• In the replacement of an existing mill control we recommend to use new installation parallel with old system
  • Will run it once a week for 1-2 months and this way it will not have interfere with the old system
  • Our engineers then complete transfer over to new system once satisfied everything is working. Usually 1 -3 days stopped production to check wiring and signals and then 2 days  production testing depending on size of mill